The massive 875,000-square-foot Amway Centre in Orlando, Florida, is a state-of-the-art sports entertainment centre. While it is the home of the Orlando Magic basketball team, it is a flexible? venue designed to accommodate a vast array of entertainment. The facility is used for everything from a concert by the Eagles or Britney Spears, to ice hockey, to arena football, to conventions, as well as 41 regular season home games played by its major tenant, the National Basketball Associationâs Orlando Magic.
The building is a LEED-certified (Leadership in Energy and Environmental Design), sustainable, environmentally friendly design, with unmatched technology. Dispersed throughout the building is over 1,000 digital monitors, the latest in broadcasting technology, and the tallest high-definition video board in an NBA venue. To fully utilize this nearly $500 million complex, conversions from one event to the next must be done rapidlyâoften in a matter of hours. Letting the facility sit idle because of delays in conversion is not an option. Well-executed conversions help maximize facility revenue and at the same time minimize expenses. Fast and efficient conversions are critical. Like any other process, a conversion can be analysed and separated into its component activities, each requiring its own human and capital resources. The operations manager must determine when to do the conversion, how to train and schedule the crew, which tools and capital equipment is necessary, and the specific steps necessary to break down the current event and set up for the next. In addition to trying to maintain a stable crew (typically provided by local staffing companies) and to maintain control during the frenzied pace of a conversion, managers divide the workforce into cross-trained crews, with each crew operating in its own uniquely collared shirt.
At the Amway Centre, Charlie Leone makes it happen. Charlie is the operations manager, and as such, he knows that any conversion is loaded with complications and risks? Concerts add a special risk because each concert has its own idiosyncrasies and the breakdown for the Eagles concert will be unique. Charlie and his crews must anticipate and eliminate any potential problems. Charlieâs immediate issue is making a schedule for converting the Eaglesâ concert venue to an NBA basketball venue. The activities and the time for various tasks have been determined and are shown in Table 15.3.


Discussion Questions
1. Make a Gantt chart to help Charlie organize his crew to perform the concert-to-basketball conversion. Note: Do not include the teardown of the concert stage and equipment, as that is the responsibility of the concert crew.
2. What time will the floor be ready?
3. Does Charlie have any extra personnel or a shortage of personnel? If so how many?
> The overall average of a process you are attempting to monitor at Feryal Erhun Enterprises is 50 units. The average range is 4 units. The sample size you are using is n = 5. a) What are the upper and lower control limits of the 3-sigma mean chart? b) Wha
> The overall average of a process you are attempting to monitor at Gihan Edirisinghe Motors is 75 units. The process standard deviation is 1.95, and the sample size is n = 10. What would be the upper and lower control limits for a 3-sigma control chart?
> The accounts receivable department at Rick Wing Manufacturing has been having difficulty getting customers to pay the full amount of their bills. Many customers complain that the bills are not correct and do not reflect the materials that arrived at thei
> Telephone inquiries of 100 IRS “customers” are monitored daily at random by Xiangling Hu. Incidents of incorrect information or other nonconformities (such as impoliteness to customers) are recorded. The data for last
> The school board is trying to evaluate a new math program introduced to second-graders in five elementary schools across the county this year. A sample of the student scores on standardized math tests in each elementary school yielded the following data:
> Frito-Lay, the multi-billion-dollar subsidiary of food and beverage giant PepsiCo, maintains 36 plants in the U.S. and Canada. These facilities produce dozens of snacks, including the well-known Lay’s, Fritos, Cheetos, Doritos, Ruffles, and Tostitos bran
> An ad agency tracks the complaints, by week received, about the billboards in its city: a) What type of control chart would you use to monitor this process? Why? b) What are the 3-sigma control limits for this process? Assume that the historical complain
> Peter Ittig’s department store, Ittig Brothers, is Amherst’s largest independent clothier. The store receives an average of six returns per day. Using z = 3, would 9 returns in a day warrant action?
> Jamison Kovach Supply Company manufactures paper clips and other office products. Although inexpensive, paper clips have provided the firm with a high margin of profitability. Sample size is 200. Results are given for the last 10 samples: a) Establish up
> The overall average on a process you are attempting to monitor is 50 units. The process population standard deviation is 1.72. Determine the upper and lower control limits for a mean chart, if you choose to use a sample size of 5. a) Set z = 3. b) Now se
> Houston North Hospital is trying to improve its image by providing a positive experience for its patients and their relatives. Part of the “image” program involves providing tasty, inviting patient meals that are also
> Five data entry operators work at the data processing department of the Birmingham Bank. Each day for 30 days, the number of defective records in a sample of 250 records typed by these operators has been noted, as follows: a) Establish 3
> Refer to Problem S6.16. If the defective rate was 3.5% instead of 1.5%, what would be the control limits (z = 3)? Data from Problem S6.16: In the past, the defective rate for your product has been 1.5%. What are the upper and lower control chart limits
> In the past, the defective rate for your product has been 1.5%. What are the upper and lower control chart limits if you wish to use a sample size of 500 and z = 3?
> The results of an inspection of DNA samples taken over the past 10 days are given below. Sample size is 100. a) Construct a 3-sigma p-chart using this information. b) Using the control chart in part (a), and finding that the number of defectives on the n
> You are attempting to develop a quality monitoring system for some parts purchased from Charles Sox Manufacturing Co. These parts are either good or defective. You have decided to take a sample of 100 units. Develop a table of the appropriate upper and l
> Orlando’s Arnold Palmer Hospital, founded in 1989, specializes in treatment of women and children and is renowned for its high-quality rankings (top 10% of 2,000 benchmarked hospitals), its labour and delivery volume (more than 14,000 births per year), a
> The defect rate for data entry of insurance claims at Sadegh Kazemi Insurance Co. has historically been about 1.5%. a) What are the upper and lower control chart limits if you wish to use a sample size of 100 and 3-sigma limits? b) What if the sample siz
> Eagletrons are all-electric automobiles produced by Mogul Motors, Inc. One of the concerns of Mogul Motors is that the Eagletrons be capable of achieving appropriate maximum speeds. To monitor this, Mogul executives take samples of 8 Eagletrons at a time
> Twelve samples, each containing five parts, were taken from a process that produces steel rods at Emmanuel Kodzi’s factory. The length of each rod in the samples was determined. The results were tabulated and sample means and ranges wer
> A process that is considered to be in control measures an ingredient in ounces. Below are the last 10 samples (each of size n = 5) taken. The population process standard deviation, , is 1.36. a) What is x? b) If z = 3,
> Boxes of Honey-Nut Oatmeal are produced to contain 14 ounces, with a standard deviation of .1 ounces. Set up the 3-sigma x-chart for a sample size of 36 boxes.
> The Head of Department of your college is concerned about the poor outcomes. He has recorded data presented in the table below for 10 students. He first investigated the students’ attendance rate and their grade to understand if there i
> Develop a histogram of the transportation time you took the last ten times you travelled to college.
> Identify and explain six quality inspections in a service with which you have had some experience.
> Choose criteria for a checklist to identify the quality problems (possible defect issues) for manufacturing shirts and blouses.
> Draw a fish-bone chart showing why an assistant you paid to prepare a spreadsheet produced one with numerous errors.
> Alaska Airlines operates in a land of rugged beauty, crystal clear lakes, spectacular glaciers, majestic mountains, and bright blue skies. But equally awesome is its operating performance. Alaska Airlines consistently provides the industry’s number-one o
> Prepare a fish-bone chart explaining how a pizza delivery can arrive late on a Friday or Saturday.
> New World Theatre tracks customer satisfaction in their cinema. In a recent survey, they asked for feedback from the customers where each customer had the opportunity to mention one thing they were displeased with. The outcome was that 797 customers answ
> Your team has been hired by a wallets producer company called Middle Eastern Fine Leather Company (MEFL). MEFL makes wallets and supplies them through several retail outlets in the Middle Eastern region. Recently some problems have emerged: â€
> Your operations management professor is a dedicated professor. He is a perfectionist, and passionate about his job. He joined your university in the fall of 2016, and has since then taught more than 500 students. A committed pedagogue, your professor exp
> Develop an Ishikawa diagram to depict customer dissatisfaction at a pizza restaurant. You should use the four Ms approach.
> Mercedes is assessing which of two windshield suppliers provides a better environmental design for disassembly. Using the tables below, select between PG Glass and Glass Unlimited.
> In Problem S5.7, another alternative (Alternative Four) is investigated, where the city takes total responsibility for the program and employs a number of local people with a variable cost of €1,000 per month. Further, in the spirit of social responsibil
> In a municipality where a significant amount of recyclable waste is generated, the city has granted permits to waste collectors to take charge of the recyclables and generate additional income by selling them. Now the city wants to establish an environme
> Repeat Problem S5.4 but now with an average fuel price of $3.8 per mile. Data from Problem S5.4: A small commercial company wants to buy cars for its sales personnel. After extensive market research, the company is about to decide which one of the follo
> In Problem S5.4, fuel efficiency was determined based on using the cars in city traffic. Estimate the total life cycle cost of each alternative and the crossover point in both miles and years if the cars are used for motorway travelling where the average
> Whether it’s scheduling nurses at Mayo Clinic, pilots at Southwest Airlines, classrooms at UCLA, or servers at a Hard Rock Cafe, it’s clear that good scheduling is important. Proper schedules use an organization’s assets (1) more effectively, by serving
> A small commercial company wants to buy cars for its sales personnel. After extensive market research, the company is about to decide which one of the following two cars to choose from based on the information provided in the following table. Compare the
> Using the information in Problem S5.1, which design alternative is the better environmental choice if the Brew House decided to remove the timer from the Brew Master model? Data from Problem S5.1: The Brew House needs to decide which of two coffee maker
> The table below compares the accuracy of two forecasting methods used by company XYZ to forecast its monthly sales of one of its product. The data pertain to the forecast and actual sales levels over a period of 5 months. What is the value of the trackin
> Using the information in Problem S5.1, which design alternative is the better environmental choice if the Brew House decided to add a timer to the Brew Mini model? The timer revenue and costs are identical to those of the Brew Master. Data from Problem
> Given the following data, use least-squares regression to develop a relation between the number of rainy summer days and the number of games lost by the Boca Raton Cardinal baseball team.
> The accountant at Bintong Chen Coal Distributors, Inc., in Newark, Delaware, notes that the demand for coal seems to be tied to an index of weather severity developed by the U.S. Weather Bureau. When weather was extremely cold in the U.S. over the past 5
> A study to determine the correlation between bank deposits and consumer price indices in Birmingham, Alabama, revealed the following (which was based on n = 5 years of data): a) What is the equation of the least-squares regression line? b) Find the coeff
> The following multiple regression model was developed to predict job performance as measured by a company job performance evaluation index based on a pre-employment test score and college grade point average (GPA): a) Forecast the job performance index f
> Using the new crossover point in Problem S5.18, how many years does it take to reach that point? Data from Problem S5.18: Using the data from Problem S5.16, if gas prices rose to $3.00 per gallon, what would be the new crossover point in miles? Data fr
> Using the date in Problem 4.47, the company wants to find out how closely sales are related to the money spent on advertisements. a) Calculate the coefficient of correlation for the data given in Problem 4.47 and comment on the degree of the linear relat
> Using the data from Problem S5.16, if gas prices rose to $3.00 per gallon, what would be the new crossover point in miles? Data from Problem S5.16: Given the data in Problem S5.15 and an alternative hybrid vehicle with the specifications shown below: a)
> Based the crossover point in miles found in Problem S5.16, what is this point in years? Data from Problem S5.16: Given the data in Problem S5.15 and an alternative hybrid vehicle with the specifications shown below: a) What is the crossover point in mil
> Given the data in Problem S5.15 and an alternative hybrid vehicle with the specifications shown below: a) What is the crossover point in miles? b) Which vehicle is having the lowest cost until the crossover point is reached? Data from Problem S5.15: Har
> Hartley Auto Supply delivers parts to area auto service centres and is replacing its fleet of delivery vehicles. What is the total vehicle life cycle cost of this gasoline engine truck given the information provided in the following table?
> Janice Carrillo, a Gainesville, Florida, real estate developer, has devised a regression model to help determine residential housing prices in north-eastern Florida. The model was developed using recent sales in a particular neighbourhood. The price (Y)
> Kalamia Company tries to forecast the value of its business based on money spent on advertising. The company has been tracking the relationship between sales and money spent on advertising, summarized in the table below (all numbers expressed in thousand
> Green Forever’s challenge (see Problem S5.12) is to determine which design alternative is the better environmental choice if it uses a different battery for the Premium Mate. The alternate battery revenue and costs are as follows: a) Wh
> Green Forever (see Problem S5.12) has decided to add an automatic string feeder system with cost and revenue estimates as shown below to the GF Deluxe model. a) What is the new revenue retrieval value for each model? b) Which model is the better environm
> Green Forever, a manufacturer of lawn equipment, has preliminary drawings for two grass trimmer designs. Charla Fraley’s job is to determine which is better environmentally. Specifically, she is to use the following data to help the com
> A Southern Georgia school district is considering ordering 53 propane-fuelled school buses. “They’re healthier, they’re cleaner burning, and they’re much quieter than the diesel option,” said a school administrator. Propane-powered buses also reduce gree
> In 2018, George Wright started the Old Oregon Wood Store to manufacture Old Oregon tables. Each table is carefully constructed by hand using the highest-quality oak. Old Oregon tables can support more than 500 pounds, and since the start of the Old Orego
> A careful analysis of the cost of operating an automobile was conducted by accounting manager Dia Bandaly. The following model was developed: y^ = 4,000 + 0.20x Where y^ is the annual cost and x is the miles driven. a) If the car is driven 15,000 miles t
> The director of the Riley County, Kansas, library system would like to forecast evening patron usage for next week. Below are the data for the past 4 weeks: a) Calculate a seasonal index for each day of the week. b) If the trend equation for this problem
> Thamer Almutairi, owner of Almutairi’s Department Store, has used time-series extrapolation to forecast retail sales for the next 4 quarters. The sales estimates are $120,000, $140,000, $160,000, and $180,000 for the respective quarters. Seasonal indices
> Given the following data, use least-squares regression to derive a trend equation. What is your estimate of the demand in period 7? In period 12?
> Sales of industrial vacuum cleaners at Larry Armstrong Supply Co. over the past 13 months are shown below: a) Using a moving average with three periods, determine the demand for vacuum cleaners for next February. b) Using a weighted moving average with t
> Environmentally conscious Susan has been told that a new electric car will only generate 6 ounces of greenhouse gases (GHGs) per mile, but that a standard internal combustion car is double that at 12 ounces per mile. However, the nature of electric cars
> A company is investigating the make-or-buy decision for a new item with the following cost structure: a) At what volumes would each decision be preferred? b) What is the most economical decision for a volume of 15,000 units per year?
> Registration numbers for an accounting seminar over the past 10 weeks are shown below: a) Starting with week 2 and ending with week 11, forecast registrations using the naïve forecasting method. b) Starting with week 3 and ending with week 1
> Perform a “product-by-value” analysis on products A, B, C, D, and E.
> A company has developed a promising new product and examines the following three alternatives of manufacturing. Alternative 1 is to buy a semiautomatic machine with an initial cost of €130,000. Alternative 2 is to buy a fully automatic machine with an in
> Wheeled Coach, the world’s largest manufacturer of ambulances, builds thousands of different and constantly changing configurations of its products. The custom nature of its business means lots of options and special designs—and a potential scheduling an
> Prepare a bill of material for a mechanical pencil.
> Prepare a bill of material for a computer mouse (GeniMouse).
> Prepare a bill of material for the table illustrated:
> Prepare a bill of material for a wooden pencil, complete with eraser.
> Given the project diagram that follows, see graph (a) and the details of the accompanying table. How can you reduce the completion time of the project by 4 weeks in the most economical way?
> Prepare a bill of material and an assembly chart for a salad of your own choosing.
> A logistics company has been in business for 4 years and wants to develop monthly indices. Monthly inventory quantities for these years are shown in the table below. a) Develop monthly indices. b) Estimate next year’s forecast for the m
> Janice Eliasson must complete the activities in the following table to finish her consulting project. a) Draw the appropriate PERT diagram. b) Find the critical path and project completion time. c) Find the probability that the project will take more tha
> A small software development project at Krishna Dhir’s firm has five major activities. The times are estimated and provided in the following table. a) Find the expected completion time for this project. b) What variance value would be u
> A warehouse manager wants to estimate the inventory moving in and out of his warehouse each week. An analyst suggests using a 3-, 5-, or 7-week moving average. However, before deciding, he wants to compare the accuracy of each for the most recent 10-week
> With vast experience at venues such as the American Airlines Arena (in Miami), the Kentucky Derby, and Super Bowls, Chef John Nicely now also plans huge culinary events at Orlando’s Amway Centre, home of the Orlando Magic basketball tea
> Regal Marine, one of the U.S.’s 10 largest power-boat manufacturers, achieves its mission—providing luxury performance boats to customers worldwide—using the strategy of differentiation. It differentiates its products through constant innovation, unique
> Develop the BOM for product XYZ made from two units of B, five units of C, and four units of D. B is sub assembled from six units of E and two units of F; C from four units of E and three units of D, and D from two units of G and four units of H.
> The actual demand for the patients at Providence Emergency Medical Clinic for the first 6 weeks of this year follows: Clinic administrator Dara Schniederjans wants you to forecast patient demand at the clinic for week 7 by using this data. You decide to
> Refer to Solved Problem 4.1. Using smoothing constants of .6 and .9, develop forecasts for the sales of VW Beetles. What effect did the smoothing constant have on the forecast? Use MAD to determine which of the three smoothing constants (.3, .6, or .9) g
> A local retailer is thinking of using exponential smoothing to forecast one of his well-selling products. His problem is that he is not sure if he should use a low or a high value of a. For this reason, he uses the historical data available and tries wit
> The following represent activities in Marc Massoud’s Construction Company project. a) Draw the network to represent this situation. b) Which activities are on the critical path? c) What is the length of the critical path?
> When is the application of a multi-domestic strategy most appropriate? What kind of industries can this be applied to?
> An air conditioner factory makes three different types of air conditioners: the ceiling type, the cassette type, and the wall mounted type. Weekly sales of each type are 2, 4, and 6 units at a price of €350, €450, and €500 each, respectively. The ceiling
> A furniture manufacturing company working on a 40-hour week makes 100 chairs. The sales price is €70 each, and the company has the following costs: ◆ Direct materials: €700 ◆ Direct labour: €300 ◆ Overhead: €500 a) Calculate the productivity of the compa
> A production operation is making 150 pieces of a product by engaging 5 workers for 300 hours. However, 40% of the units appear to have various quality problems and the company decides to sell them as seconds at a price of €50 each when the normal unit is
> Mr. Achebe, who runs his photocopy business working 8 hours per day, processes 100 scripts in a day. He estimates his labour cost to be €9 per hour. Also, he has estimated that the total material cost for each script is approximately €2 while the daily e
> Hill’s Automotive, Inc., is an aftermarket producer and distributor of automotive replacement parts. Art Hill has slowly expanded the business, which began as a supplier of hard-to-get auto air-conditioning units for classic cars and hot rods. The firm h
> You are about to establish your own business; your strategy is to focus on your core business and outsource the customer service to an external service provider to handle the customers’ requirement queries and complaints. Based on an ex
> As an operations management student, you have been hired by a local restaurant to perform a factor-rating analysis to help the restaurant choose an outsourcing provider. You have identified three important factors: quality, taste, and delivery time; givi
> Refer to Problem 4.2. Develop a forecast for years 2 through 12 using exponential smoothing with a = .4 and a forecast for year 1 of 6. Plot your new forecast on a graph with the actual data and the naive forecast. Based on a visual inspection, which for
> The table below shows the activities, immediate predecessors, and activity durations of a project. Draw the AON project network. How long would it take to complete this project? What is the length of the critical path?
> Potamia Construction Co. (PCC) is developing plans to erect a new hospital building. Potamia Construction Co. has established the project activities and their immediate predecessor activities together with their estimated activity durations according to
> Draw the AON project network using the following information: How long would it take to complete this project? Which activities are included on the critical path?