Question: The Rover 6 is a new custom-

The Rover 6 is a new custom-designed sports car. An analysis of the task of building the Rover 6 reveals the following list of relevant activities, their immediate predecessors, and their duration:
The Rover 6 is a new custom-designed sports car. An analysis of the task of building the Rover 6 reveals the following list of relevant activities, their immediate predecessors, and their duration:


a) Draw a network diagram for the project.
b) Mark the critical path and state its length.
c) If the Rover 6 had to be completed 2 days earlier, would it help to?
i) Buy preassembled transmissions and drive trains?
ii) Install robots to halve engine-building time?
iii) Speed delivery of special accessories by 3 days?
d) How might resources be borrowed from activities on the noncritical path to speed activities on the critical path?

a) Draw a network diagram for the project. b) Mark the critical path and state its length. c) If the Rover 6 had to be completed 2 days earlier, would it help to? i) Buy preassembled transmissions and drive trains? ii) Install robots to halve engine-building time? iii) Speed delivery of special accessories by 3 days? d) How might resources be borrowed from activities on the noncritical path to speed activities on the critical path?





Transcribed Image Text:

JOB IMMEDIATE NORMAL LETTER DESCRIPTION PREDECESSOR(s) TIME (DAYS) A Start - B Design A 8 Order special accessories B 0.1 Build frame B 1 E Build doors B 1 F Attach axles, wheels, D 1 gas tank G Build body shell B 2 Build transmission and drivetrain H B Fit doors to body shell G, E 1 Build engine B 4 K Bench-test engine 2 L Assemble chassis F. H, К 1 M Road-test chassis L 0.5 N Paint body 2 Install wiring N Install interior 1.5 Accept delivery of special accessories Q 5 Mount body and accessories on chassis М, О., Р. О 1 Road test car R 0.5 Attach exterior trim 1 Finish P. R.


> What are the requirements for a focused work center or focused factory to be appropriate?

> What are the alternative forms of work cells discussed in this textbook?

> What are the three factors that complicate a fixed-position layout?

> What are the seven layout strategies presented in this chapter?

> The estimated times and immediate predecessors for the activities in a project at George Kyparis’s retinal scanning company are given in the following table. Assume that the activity times are independent. a) Calculate the expected ti

> List the techniques used by service organizations to select locations.

> Why shouldn’t low wage rates alone be sufficient to select a location?

> Explain the assumptions behind the center-of-gravity method. How can the model be used in a service facility location?

> List factors, other than globalization, that affect the location decision.

> Although most organizations may make the location decision infrequently, there are some organizations that make the decision quite regularly and often. Provide one or two examples. How might their approach to the location decision differ from the norm?

> What factors affect region/community location decisions?

> Provide two examples of clustering in the service sector.

> What are the advantages and disadvantages of a qualitative (as opposed to a quantitative) approach to location decision making?

> How does factor weighting incorporate personal preference in location choices?

> What is clustering?

> Kelle Carpet and Trim installs carpet in commercial offices. Peter Kelle has been very concerned with the amount of time it took to complete several recent jobs. Some of his workers are very unreliable. A list of activities and their optimistic completio

> Lillian Fok is president of Lakefront Manufacturing, a producer of bicycle tires. Fok makes 1,000 tires per day with the following resources: a) What is the labor productivity per labor-hour for these tires at Lakefront Manufacturing? b) What is the mu

> Why do so many foreign companies build facilities in the U.S.?

> Why do so many U.S. firms build facilities in other countries?

> How is FedEx’s location a competitive advantage? Discuss.

> What is additive manufacturing?

> In what ways do CAD and FMS connect?

> Name some of the advances being made in technology that enhance production and productivity.

> Identify service firms that compete on each of the four processes shown in Figure 7.1. Reference Figure 7.1: *****..*......... ... I Figure 7.1 Volume Process Selected Must Fit with Volume and Variety Low Volume Repetitive Process High Volume Proce

> Identify manufacturing firms that compete on each of the four processes shown in Figure 7.1. Reference Figure 7.1: *****..*......... ... I Figure 7.1 Volume Process Selected Must Fit with Volume and Variety Low Volume Repetitive Process High Volume

> What do we mean by a process-control system, and what are the typical elements in such systems?

> What is CIM?

> A renovation of the gift shop at Orlando Amway Center has six activities (in hours). For the following estimates of a, m, and b, calculates the expected time and the standard deviation for each activity: ACTIVITY a m b A 11 15 19 B 27 31 41 18 18 18

> Name the four quadrants of the service process matrix. Discuss how the matrix is used to classify services into categories.

> What are the techniques for improving service productivity?

> What is process redesign?

> What is service blueprinting?

> What type of process is used for making each of the following products? (a) beer (b) wedding invitations (c) automobiles (d) paper (e) Big Macs (f ) custom homes (g) motorcycles

> What is process strategy?

> Name several products that do not require high quality.

> What are 10 determinants of service quality?

> Explain, in your own words, what is meant by source inspection.

> What roles do operations managers play in addressing the major aspects of service quality?

> Ross Hopkins, president of Hopkins Hospitality, has developed the tasks, durations, and predecessor relationships in the following table for building new motels. Draw the AON network and answer the questions that follow. a) What is the expected (estima

> What are the four broad categories of “causes” to help initially structure an Ishikawa diagram or cause-and-effect diagram?

> What is the purpose of using a Pareto chart for a given problem?

> List the three concepts central to Taguchi’s approach.

> Philip Crosby said that quality is free. Why?

> How can a university control the quality of its output (that is, its graduates)?

> How does fear in the workplace (and in the classroom) inhibit learning?

> What are seven tools of TQM?

> Name three of the important people associated with the quality concepts of this chapter. In each case, write a sentence about each one summarizing his primary contribution to the field of quality management.

> List the seven concepts that are necessary for an effective TQM program. How are these related to Deming’s 14 points?

> As an Internet exercise, determine the Baldrige Award criteria. See the Web site www.nist.gov/baldrige/.

> Explain how improving quality can lead to reduced costs.

> Why are the direct interactions and surrogate interaction regions in a PCN diagram important in service design?

> What is a process chain?

> Explain how the house of quality translates customer desires into product/service attributes.

> Explain what is meant in service design by the “moment of truth.”

> What information is contained in an assembly chart? In a process sheet?

> What information is contained in an engineering drawing?

> What information is contained in a bill of material?

> What are three specific ways in which computer-aided design (CAD) benefits the design engineer?

> Explain what is meant by robust design.

> Dave Fletcher (see Problem 3.12) was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path s

> Describe the differences between joint ventures and alliances.

> What is time-based competition?

> Once a product is defined, what documents are used to assist production personnel in its manufacture?

> In what ways is product strategy linked to product decisions?

> What techniques do we use to define a product?

> As an approach to inventory management, how does MRP differ from the approach taken in Chapter 12 , dealing with economic order quantities (EOQ)?

> What are the typical benefits of ERP?

> Identify five specific requirements of an effective MRP system.

> Master schedules are expressed in three different ways depending on whether the process is continuous, a job shop, or repetitive. What are these three ways?

> MRP is more than an inventory system; what additional capabilities does MRP possess?

> The following is a table of activities associated with a project at Rafay Ishfaq’s software firm in Chicago, their durations, and what activities each must precede: a) Draw an AON diagram of the project, including activity durations.

> What are the similarities between MRP and DRP?

> Once a material requirements plan (MRP) has been established, what other managerial applications might be found for the technique?

> What is the difference between a gross requirements plan and a net requirements plan?

> What are major limitations of using the transportation method for aggregate planning?

> Why are graphical aggregate planning methods useful?

> What is the relationship between the aggregate plan and the master production schedule?

> Define mixed strategy. Why would a firm use a mixed strategy instead of a simple pure strategy?

> What is level scheduling? What is the basic philosophy underlying it?

> What information is necessary for random stocking to work?

> What layout variables would you consider particularly important in an office layout where computer programs are written?

> The activities described by the following table are given for the Howard Corporation in Kansas: a) Draw the appropriate AON PERT diagram for J.C. Howard’s management team. b) Find the critical path. c) What is the project completion t

> What are the advantages and disadvantages of work cells?

> What are the four assumptions (or preconditions) of establishing layout for high-volume, low variety products?

> What are the advantages and disadvantages of product layout?

> How would an analyst obtain data and determine the number of trips in: (a) a hospital? (b) a machine shop? (c) an auto-repair shop?

> What are the advantages and disadvantages of process layout?

> Explain the concept of cross-docking.

> Manufacturers locate near their resources, retailers locate near their customers.” Discuss this statement, with reference to the proximity-to-markets arguments covered in the text. Can you think of a counter-example in each case? Support your choices.

> What are the three steps to locational cost–volume analysis?

> What are the major factors that firms consider when choosing a country in which to locate?

> Contrast the location of a food distributor and a supermarket. (The distributor sends truckloads of food, meat, produce, etc., to the supermarket.) Show the relevant considerations (factors) they share; show those where they differ.

> Task time estimates for the modification of an assembly line at Jim Goodale’s Carbondale, Illinois, factory are as follows: a) Draw the project network using AON. b) Identify the critical path. c) What is the expected project length?

> Explain what a flexible manufacturing system (FMS) is.

> Describe briefly what an automatic identification system (AIS) is and how service organizations could use AIS to increase productivity and at the same time increase the variety of services offered.

> What are numerically controlled machines?

> Identify the competitive advantage of each of the four firms identified in Discussion Question 11.

> Identify the competitive advantage of each of the four firms identified in Discussion Question 9.

> Discuss the advantages and disadvantages of 3D printing.

> Of the several points where inspection may be necessary, which apply especially well to manufacturing?